After a successful initial verification test on a repaired R-123 chiller that was not evacuated, how soon…

Leak repair requirements · EPA 608 Type III. The correct answer, and the reasoning behind it.

Allowable annual leak rates for low-pressure appliances.

The question

After a successful initial verification test on a repaired R-123 chiller that was not evacuated, how soon must the follow-up verification test be done?

  • Within 30 days
  • Within 10 daysCorrect answer
  • Within 24 hours
  • Within 12 months

Why “Within 10 days” is correct

40 CFR 82.157(e)(2) requires a follow-up verification test within 10 days of the successful initial test. If the appliance was evacuated for the repair, the 10 days run from when it reaches normal operating conditions.

Source: 40 CFR 82.157(e)

Why the other answers are wrong

  • Within 30 days — 30 days is the repair deadline, not the follow-up test window.
  • Within 24 hours — The rule allows 10 days, not one day.
  • Within 12 months — 12 months relates to presuming leaks repaired, not to follow-up testing.

Practice more of this

More EPA 608 Type III practice questions, or see every EPA 608 practice test.