To what level must the appliance be evacuated before it is opened?
Recovery requirements · EPA 608 Type II. The correct answer, and the reasoning behind it.
Evacuation levels by charge size and equipment date, major repairs, and system-dependent limits.
The question
A technician is replacing the compressor on a very high-pressure appliance that uses R-23, using recovery equipment manufactured in 2019. To what level must the appliance be evacuated before it is opened?
- 0 inches of Hg vacuumCorrect answer
- 4 inches of Hg vacuum
- 10 inches of Hg vacuum
- 15 inches of Hg vacuum
Why “0 inches of Hg vacuum” is correct
Table 1 sets a single level for very high-pressure appliances: 0 inches of Hg vacuum, whatever the recovery equipment date or charge size. R-23 is one of the examples EPA gives of a very high-pressure refrigerant.
Source: 40 CFR 82.156(a), Table 1; 40 CFR 82.152
Why the other answers are wrong
- 4 inches of Hg vacuum — 4 inches applies to some medium- and high-pressure rows with pre-1993 equipment, not to very high-pressure appliances.
- 10 inches of Hg vacuum — 10 inches is for large high-pressure or small medium-pressure appliances with newer equipment.
- 15 inches of Hg vacuum — 15 inches is only for medium-pressure appliances of 200 pounds or more with newer equipment.
Practice more of this
More EPA 608 Type II practice questions, or see every EPA 608 practice test.
Unofficial, not affiliated with the EPA or any EPA-approved certifying organization. Questions are original practice written from public EPA material, not real exam questions.